Appendix 11: Sample budget

Budget
<Project name>
<Project phase: initiation – evaluation >
<Name of the person compiling this document >
<date>
Amount in Euros
 
Initiation phase Who? Hours Fee Total
 
Research draft Project Leader 20 75 1500
Consultation with partners Project Leader 10 75 750
Preparation of project proposal Department Head 40 80 3200
Proposal design Graphic Design 10 50 500
Contract expertise     1000 1000
       
subtotal initiation phase: 6950
Definition phase
 
Consultation with end users Project Leader 10 75 750
  Functional Designer 10 65 650
Consultation with experts Project Leader 20 75 1500
  Functional Designer 30 65 1950
  Internal Experts 30 100 3000
Contract expertise       2500
Catering for meetings       250
Project management   25 75 250
 
subtotal definition phase: 10850
 
Design phase
 
Travel costs Team Members     1000
Design sketch Designer 60 60 3600
Design presentation Designer 20 60 1200
Materials       2000
Web presentation
Content Content 20 60 1200
HTML Programmer 20 65 1300
Design Designer 30 60 1800
Project management   15 75 1125
 
    subtotal design phase: 13225
Preparation phase
 
Travel costs       2000
Material costs       15000
Elaboration of schedules Project Leader 40 75 3000
Project management   15 75 1125
 
subtotal preparation phase: 22125
 
Implementation phase
 
Travel costs (personnel)       2000
Material transport costs       3000
Operations (internal personnel) Carpenters 160 45 7200
  Plumbers 160 50 8000
  Designers 80 65 5200
Temporary workers       25000
Gas, water, electricity       3000
Project management   80 75 6000
 
subtotal implementation phase: 59400
 
Follow-up phase
 
Travel costs (personnel)       2000
Material disposal       3000
Material clean-up project team 40 60 2400
Final report Project Leader 40 75 3000
Accountant�s statement       1000
Project management   40 75 3000
 
subtotal follow-up: 15900
 
Summary
 
subtotal initiation phase: 6950
subtotal definition phase: 10850
subtotal design phase: 13225
subtotal preparation phase: 22125
subtotal implementation phase: 59400
subtotal follow-up: 15900
 
subtotal: 128450
unexpected costs 10% 13495
 
total: 141945
 
This budget is a global estimate of the entire <project name>. project. At the beginning of each new phase, a detailed budget for that phase is delivered.